Caring,
Fixing, Planning...
Take
care of what we have, fix what needs it, and plan for the future!
These words are pretty simple but convey the essence of Helix's
comprehensive Capital Improvement Program.
In the 50-square-mile area served by Helix, there are about 700
miles of pipes, 25 pump stations, 22 storage tanks, and the 30-million-gallon
underground Grossmont Reservoir located under much of Harry Griffen
Park in La Mesa. All of the water for the Valley and other unincorporated
areas is treated and tested at the R.M. Levy Treatment Plant in
Lakeside.
See Bid
Results
See
Plan
Holder List
Current Projects:
Ball Pump Station Power Upgrade (WO 1795)
In Construction
Construction Start Date: November 2009
Estimated Construction End Date: January 2011
Project Cost: $1,656,000
Project Manager:
Luis Valdez
Description:
The Ball Pump Station Power Upgrade, WO 1795, consists of modifications
to the existing Ball Pump Station in the County of San Diego.
The pump station currently has two diesel drivers for the two
600 horsepower pumps capable of pumping 31,250 gallons per minute
each. The Air Pollution Control District permit for the existing
diesel generators is expected to expire in January 2011. The project
involves installation of electric motor drivers to replace the
diesel drivers for the pumps and associated structural, piping,
electrical, and instrumentation work. Construction duration including
electric motor procurement is estimated at 15 months. Map
Cast-Iron Pipeline Replacement Program
The District
prepared a Cast-Iron Pipeline Replacement Master Plan in 2005
that identified 64 miles of existing cast-iron pipe in need of
replacement. A 14-year program was developed to replace approximately
5 miles of cast-iron pipeline per year. Cast-iron pipe is susceptible
to corrosion and leaks, and the District has proactively been
replacing the cast-iron piping within the system with PVC pipe.
The new PVC pipelines reduce the property damage potential, provide
our customers with more reliable service and better fire projection,
and requires less maintenance by District crews. The estimated
cost of the Cast-Iron Replacement Program is $85 million. During
the first four fiscal years, the District has replaced approximately
15 miles of cast-iron pipeline.

Pipeline
Project 1400
In Construction
Construction Start Date: April 2009
Estimated Construction End Date: December 2009
Project Cost: $1,425,000
Project Manager:
Greg Jones
Description:
This project replaces approximately 6,500 feet of 4-inch, 6-inch,
and 10-inch cast-iron pipe in the County of San Diego. Pipeline
replacement is located in Wister Drive, Sierra Vista Avenue, Shadow
Road, Fuerte Drive, El Granito Avenue, Redondo Drive, and Easements.
Construction duration is estimated at 8 months. Map
1 and Map 2

Construction
at Helix Terrace, WO 1400; Construction at Fuerte, WO 1400
Pipeline
Project 1442
In Construction
Construction Start Date: July 2009
Estimated Construction End Date: January 2010
Project Cost: $1,333,000
Project Manager:
Chris McRae
Description:
This project replaces approximately 6,800 feet of 6-inch, 8-inch,
and 10-inch cast-iron pipe in the County of San Diego. Pipeline
replacement is located in Dawnridge Avenue, El Rey Avenue, N.
Second Street, and Pepper Drive. Construction duration is estimated
at 6 months. Map

Cast-Iron
Pipe Removed, WO 1442; Paving at Pepper, WO 1442
Pipeline Project 1818
In Construction
Construction Start Date: October 2009
Estimated Construction End Date: April 2010
Project Cost: $1,205,000
Project Manager: Darrel
Williams
Description:
This project replaces approximately 6,900 feet of 8-inch cast-iron
pipe in the County of San Diego. Pipeline replacement is located
in Ramona Drive, El Canto Drive, Toledo Road, Madrid Way, and
Pinto Place. Construction duration is estimated at 6 months. Map
Pipeline
Project 1637
Expected Bid Date: November 2009
Engineer's Estimate: $1,900,000
Project Manager:
Darrel Williams
Description:
This project replaces approximately 8,700 feet of 8-inch and 12-inch
cast-iron pipe in the County of San Diego. Pipeline replacement
is located in Alzeda Drive, Vita Road, Hess Drive, Calavo Drive,
Carmen Drive, Grove Road, and an easement near San Lori Lane.
Construction duration is estimated at 160 working days. Map
1 and Map 2

Existing
Flume Easement, WO 1637; Existing Concrete Roadway, WO 1637
Pipeline Project 2134
Expected Bid Date: March 2010
Engineer's Estimate: $920,000
Project Manager:
Chris McRae
Description:
This project replaces approximately 6,100 feet of 8-inch and 12-inch
cast-iron pipe in the County of San Diego. Pipeline replacement
is located in Annapolis Avenue, Berkeley Drive, Kemper Street,
La Mesita Place, Marian Street, Oxford Street, and Purdue Avenue.
Construction duration is estimated at 120 working days. Map