Caring,
Fixing, Planning...
Take
care of what we have, fix what needs it, and plan for the future!
These words are pretty simple but convey the essence of Helix's
comprehensive Capital Improvement Program.
In the 50-square-mile area served by Helix, there are about 700
miles of pipes, 22 storage tanks, and the 30-million-gallon underground
Grossmont Reservoir located under much of Harry Griffen Park in
La Mesa. All of the water for the Valley and other unincorporated
areas is treated and tested at the R.M. Levy Treatment Plant in
Lakeside.
Projects
Open for Bid
Recent
Bid Results
Current
Projects:
Construction
of Los Coches Pump Station (WO 219)
Bid Opening October 10, 2006 - 10:00AM
Engineers Estimate: $9,000,000
$110 Per Set of Specs/Drawings
Project Manager: Luis
Valdez
Description:
The Los Coches Pump Station Project, WO 219, consists of the construction
of a 64 million gallon per day (MGD) pump station on the site
of the Districts R.M. Levy Water Treatment Plant. A new
50 ft x 60 ft CMU building will house five 450-horsepower vertical
turbine pumps and associated equipment in the main pump room.
A separate electrical room will house electrical switchgear which
will include variable frequency drive units, electrical metering,
and control panels. Yard piping will include cement mortar lined
and coated steel pipe ranging in diameter from 36-inches to 60-inches.
The project will require civil site work to include excavation,
grading, paving and limited landscaping. An enclosed 1,500 kW
diesel generator will be installed for standby power and coordination
with SDG&E will be required for the installation of a 4,000
Amp electrical service station. The work includes demolition of
the existing pump station which consists of four outdoor vertical
turbine pumps, and demolition of an existing metal storage shed.
The construction duration is 375 working days and the Engineers
Estimate is $9 million.
Pipeline
Project 794
Fletcher
Pkwy., Broadway, North Magnolia Ave., and Entrance to Parkway
Plaza
Bid Opening August 31, 2006 - 10:00 a.m.
Engineers
Estimate: $2,100,000
$35.00 Per Set of Specs/Drawings
Project Manager: Greg
Jones
Brief Description:
This project replaces existing 12" cast-iron pipelines with
approximately 10,700ft of new 12" and 8" PVC Class 200
pipe within Fletcher Pkwy and Broadway from 200ft west of Jackman
St. to First St. And in the Entrance to Parkway Plaza and North
Magnolia Ave. from 400ft south of Fletcher to 350ft north of Fletcher.
Construction duration is 180 working days.
Pipeline Project 795
Bid Opening March 28th, 2006 -10 a.m.
Engineer's
Estimate: $ 1,661,690.00
$35 per set of specs/drawings
Project Manager:
Darrel
Williams
Brief Description:
This project replaces existing 6" and 12" cast-iron
pipelines in West Washington Avenue from South Magnolia Avenue
to 450'± west, East Washington Avenue from Lincoln Avenue
to South Third Street, Jamacha Road 186' ± north and 241'
± south. South Second Street from West Washington, north
to Andowver Road with approximately 307 feet of 6-inch, 1,141
feet of 8-inch and 9,102 feet of 12-inch class 200 PVC. Construction
duration is 190 working days.
Cast Iron
Replacement Project
This is part
of the District's continuing cast-iron pipe replacement program.
Cast-iron pipe is susceptible to corrosion and leaks, and the
District has proactively been replacing the cast-iron piping within
the system with PVC pipe. The new PVC pipelines reduce property
damage potential, provide our customers with more reliable service
and better fire protection, and requires less maintenance by District
crews.
In this particular
project, the District has contracted with Erreca's Inc. to install
4,250 feet of 8-inch PVC Class 200 pipe in various streets in
the City of Lemon Grove. The project is 75 percent complete with
an estimated completion date of April 1, 2005. The original contract
price was $493,000. Read
more...
Pipeline
Project 539
Bid Opening June
7, 2005 at 10 a.m.
Engineer's
Estimate: $1,230,000
$35
per set of specs/drawings
Project Manager:
Darrel
Williams
Brief Description:
This project replaces existing 6" and 12" cast-iron
pipelines in Ballantyne St. from Broadway to Madison Ave., Wells
Ave. from N. Magnolia Ave. to Ballantyne St., Graves Ave. from
Beech St. to Wells Ave., Beech
St. from Garves Ave. to Ballantyne St., Madison Ave. from Graves
Ave.to Ballantyne St., Graves Ave. from 285 feet south of Broadway
to Lloyd St., Cedar St. from 355 feet west of Graves Ave. to Ballantyne
St. with approximately 100 feet of 6 inch, 7,672 feet of 8 inch,
and 640 feet of 12 inch class 200 PVC construction duration is
110 working days.
Windsor Hills Tank
Replacement WO 3854
Project
Address: 4165 Arrieta Circle, La Mesa
Bid Opening: April 14, 2005 at 10 a.m.
Engineer's Estimate: $1,550,000
$35 per set of specs/drawings
Project Manager: Aneld
Anub
Brief Description:
The work consists of the demolition and disposal of an existing
1 million-gallon prestressed concrete potable water reservoir,
its foundation, underdrain system and associated piping, and construction
of a 1 million-gallon welded steel potable water reservoir. The
work includes associated foundations, pipelines, valves, vaults,
storm drain, site work, interior and exterior coatings to the
new tank, cathodic protection system, modifications to an existing
hydro pneumatic pump station and tank located on-site, removal
and reinstallation of existing level monitoring system and telemetry,
site paving, irrigation piping, landscaping, and fencing.
Pipeline Project 240
Commercial Street,
Center Street, Guild Street, Lake Murray Boulevard, Lake Park
Way, Linden Lane, Loma Vista Drive, Randlett Drive, Seneca Place
Bid opening
is April 12, 2005 at 10 a.m.
Engineer's estimate: $600,000
$35.00 per set of specs/drawings
Project manager:
Chris McRae
Brief Description:
This project replaces existing 4-inch, 6-inch, 8-inch, and 10-inch
cast-iron pipelines in and near Commercial St., Center St., Guild
St., Lake Murray Blvd., Lake Park Way, Linden Ln., Loma Vista
Dr., Randlett Dr., Seneca Pl. with approximately 4,400 feet of
new 8-inch PVC class 200 pipe. The construction duration is 60
working days.
Pipeline Project 237
Marshall
Avenue
Bid opening is March 8 at 10 a.m.
Engineer's estimate: $855,430
$35 per set of specs/drawings
Project manager: Darrel
Williams
Brief Description:
This project replaces existing 12-inch and 6-inch cast-iron pipelines
in Marshall Avenue from West Main Street to El Cajon Boulevard,
Palm Avenue from Marshall Avenue to Millar Avenue, Millar Avenue
from Palm Avenue to 860 feet ± south, S. Sunshine Avenue
from W. Washington Avenue to W. Renette Avenue, W. Renette Avenue
from S. Sunshine Avenue to 150 feet ± west, and N. Third
Street from Greenfield Drive to Luke Lane with Approximately 5,605
feet of 8-inch Class 200 PVC, and 1,018 feet of 12-inch Class
200 PVC. The construction duration is 90 working days.
Windsor
Hills "B" Tank Replacement
4165 W. Arrieta Circle, La Mesa.
The
existing prestressed concrete reservoir was built in 1958. A 1988
study indicated that the Windsor Hills "B" Tank did
not meet current seismic standards and the roof was cracked.
The
report also noted that the Windsor Hills "B" Tank is
considered the fourth most strategically important reservoir in
the District's system. Replacing this reservoir will meet current
seismic standards and ensure a sound system to serve the public.
The work consists of the demolition and disposal of an existing
1 million-gallon prestressed concrete potable water reservoir
and associated piping, and construction of a 1 million-gallon
welded steel potable water reservoir.
The work includes associated foundations, pipeline, valves, storm
drains, site work, tank coatings, cathodic protection system,
modifications to existing hydropneumatic pump station and tank
located on-site, site paving, irrigation piping, landscaping,
and fencing.
Design of the tank replacement is expected to be completed in
March 2005, and advertise for bids from contractors in April 2005.
Construction is expected to start in May 2005 and last about 9
months. The Engineer's estimated construction cost is $1.5 million.
Construction of Homelands Pump Station:
2050A
Greenfield Dr., El Cajon
This project involves the construction of the Homelands Pump Station
on a new site next to the Greenfield Tank. This facility will
replace the old Homelands Pump Station which was abandoned after
the relocation of the Flume Transmission Main in 2000.
| |
 |
 |
|
The new pump
station consists of three 125 horsepower pumps, which will restore
a permanent primary service to the Homelands area east of El Cajon,
as well as provide backup service to neighboring areas. The pump
station project includes associated site improvements, installation
of piping, valves and other mechanical/electrical equipment. The
facility will be housed in a masonry building that has been designed
to mitigate both noise and visual impacts to the surrounding community.
Construction of the pump station, which started in July 2004,
is expected to be completed in May 2005. The Contractor is Ryan
Company and the construction contract is $1.3 million.
Construction
of Moreno Lakeside Pipeline:
The Moreno
Lakeside Pipeline (MLP) is a joint project between the San Diego
County Water Authority and the Helix Water District. The pipeline
is a new 4.7-mile raw water transmission main consisting of 54-inch
and 60-inch segments of cement-mortar-lined and coated steel pipe.
This pipeline will augment the District's raw water transmission
capacity from the Authority's raw water Aqueduct No.1, and will
ultimately allow for the District to receive water from the San
Vicente Reservoir. The pipeline will have a capacity of 80 mgd,
of which 40 mgd is reserved for Helix WD.
The pipeline project includes an interconnect vault which connects
the MLP to the District's other raw water transmission mains near
the R.M. Levy Water Treatment Plant to provide additional raw
water delivery flexibility to the treatment plant. Construction
of the MLP Project began in Fall 2002 and will be completed by
the end of February 2005. The Contractor is Archer Western Contractors.
Construction cost is $18 million.
Replacement
of Filter Valves at WTP:
This is a
District project that involves replacement of five 30-inch filter
influent valves and six 16-inch filter surface wash valves at
the water treatment plan. This replaces the valves that were in
continuous service since the initial construction of the treatment
plant in 1963.
The valve equipment was procured by the district in mid 2004 and
was installed by District treatment plant personnel in November
2004. Because this project replaced the original valves, which
were worn and required much attention, everyday operations and
maintenance is enhanced with the installation of the new equipment.
Project cost is $160,000.